Booral Road, Bunya Creek floodway and Main Street intersection upgrade, planning

Planning is underway to improve flood immunity and safety on a section of Booral Road at Bunya Creek, including the Main Street intersection.

The Bunya Creek floodway directly west of the Main Steet intersection is frequently inundated, resulting in road closures for through traffic forcing road users to use alternate routes.

Planning will assess the current and future transport requirements at the intersection.

This project involves delivering a business case which identifies an appropriate upgrade treatment to improve safety and flood immunity for all road users.

This is a planning project only, there is no timeframe nor funding for construction.

Benefits

  • Improves safety
  • Improves network efficiency
  • Improves flood immunity
  • Reduces travel time
  • Contributes to economy
  • Contributes to regional growth
  • Improves ride quality

Key features

  • Consultation with key stakeholders to identify issues.
  • Develop a business case to propose safety upgrades and flood immunity for future funding.

Funding

This project is fully funded by the Queensland Government. Investment ID 1133855

Total investment
$725,000
Queensland Government
$725,000

Current status

We are currently undertaking planning.

Booral Road Bunya Creek floodway and Main Street intersection upgrade project map