10 Year Forward Plan (2018-2028)
Program map
Upgrade projects
Mount Lindesay Highway (Brisbane–Beaudesert), Logan Motorway to Park Ridge Road, planning – Cost: $1.5 million
1. Logan Motorway to Park Ridge Road
- Improve connectivity, travel times and safety
- Six lane widening
- Currently in planning 2023-2027
2. Green Road/Coronation Road Interchange
- Project planning - combined with Project 1
- Increase capacity and improve travel times
- Currently in planning 2023-2027
3. Rosia Road to Stoney Camp Road
- Cost: $22.4 million
- Increase capacity and improve travel times and safety
- Delivered 2020
4. Stoney Camp Road to Chambers Flat Road
- Cost: $75 million ($37.5 million Australian Government, 37.5 million Queensland Government)
- Increase capacity and improve travel times
- Delivered 2023
5. North Maclean safety improvements
- Cost: $20 million ($16 million Australian Government, $4 million Queensland Government)
- Improve safety
- Delivered 2019
6. South Maclean safety improvements
- Cost: $14 million
- Improve safety
- Delivered 2020
Mount Lindesay Highway (Brisbane–Beaudesert), North Maclean to Jimboomba, planning – Cost: $4.1 million
7. Greenbank Road to Stockleigh Road
- Increase capacity and improve travel times, safety, reliability and flood immunity
- Currently in planning 2023-2026
8. Chambers Flat Road to Greenbank Road
- Increase capacity, improve safety and travel times
- Currently in planning 2023-2026
9. Stockleigh Road to Camp Cable Road
- Increase capacity and reliability
- Currently in planning 2023-2026
10. Camp Cable Road intersection
- Cost: $7 million
- Increased capacity, reliability and safety
- Delivered 2016
11. Camp Cable Road to Johanna Street, Jimboomba
- Cost: $19.6 million
- Increase capacity and improve travel times, safety, reliability and flood immunity
- Delivered 2020
12. Johanna Street to South Street through Jimboomba
- Cost: $57.4 million ($42.4 million Australian Government, $15 million Queensland Government)
- Increase capacity and improve travel times
- Detailed design
13. Millstream Road intersection
- Cost: $2 million
- Increased safety and improved travel times
- Delivered 2015
14. South Street to Cedar Vale Road
- Cost: $1 million (project planning)
- Increase capacity, improve safety and travel times
- Currently in planning 2023–2027
15. Cedar Vale Road to Beaudesert
- Cost: Currently unfunded
- Improve safety
- Planning beyond 2026
16. Beaudesert Town Centre Bypass
- Cost: $27.5 million
- Improved safety and reliability
- Delivered 2017
17. Jimboomba to Beaudesert safety improvements
- Cost: $17.137 million ($16.865 million Queensland Government, $0.272 million Logan City Council)
- Improve intersections
- Delivered 2021–2022